New Cartec Rail Facility - Dagenham

Client: Ford Motor Company
Contract: Period: 16 Weeks
Value: £800,000

The Construction Of A New Cartec Rail Facility To Accept 700m Long Rail Traffic Onto The Dagenham Estate.

Incorporating an existing road diversion with drainage kerbing and tarmac surfacing, thermoplastic lining and installation of Armco barriers, security fencing, high pressure fire main diversions with associated concrete thrust blocks and testing, cut & fill excavation over site, placing and levelling of new track blast to lay 800m of new track, forming concrete access strips to either side and between the new tracks with over 20,000m2 of new block paving, profiling of surrounding area.